US lawmakers are proposing bills that could end full expensing for AI‑focused data centers and add a gross‑receipts tax, raising billions in revenue but risking a shift of investment abroad.
- Warner’s Data Center Tax Accountability and Disclosure Act (July 2026) bars full expensing for any property in an “AI data center” used ≥ 20 % for AI, unless the facility earns LEED Platinum or Gold certification.
- Revenue impact (Tax Foundation TAG model): central estimate $29.9 billion, dynamic $18.2 billion, range $17.5 billion–$46.5 billion over 2027‑2036; long‑run GDP effect < 0.05 %.
- Wyden’s Data Center Tax White Paper (August 2026) proposes a low‑single‑digit percent gross receipts tax on data‑center operators, exempting “internet infrastructure,” corporate IT, “small” centers and pre‑2024 facilities (except the largest).
- A 4 % gross receipts tax could become an effective net‑income tax of 40 %–200 % depending on a firm’s expense structure.
- Both bills leave key definitions vague (how the 20 % AI usage is measured; what qualifies as “small” or “internet infrastructure”), creating administrative ambiguity.
- Risk: developers may relocate new facilities abroad, undermining the United States’ projected $581 billion AI capital‑expenditure advantage in 2026.
- Context: Goldman Sachs forecasts $1 trillion global AI spending in 2026, with $581 billion in the US; full expensing currently allows immediate deduction of equipment and building costs, supporting rapid deployment.
Takeaway: Anticipate loss of full expensing for AI data centers and a possible new gross‑receipts tax, so evaluate LEED certification options and tax‑impact models now to mitigate higher costs and potential relocation decisions.
Source article: taxfoundation.org